A further schedule of work has now been received from the Developer which, unfortunately, indicates that the completion of the engineering work to the swing bridge and access road is now likely to be mid October.
Further representations have now been made stating that the revised schedule is not acceptable. The Trust will continue to work closely with local councillors, Leeds City Council planning officers and Yorkshire Water to ensure rapid progress is made to protect the interests of the Reserve, its users and local communities.
In the interim the Sunday opening arrangements will continue with access via the canal towpath.
The Trust will continue to post information as soon as it becomes available.
Rodley Nature Reserve Trust, 28 May 2022